Koysinjaq, Iraq
Project SummaryTTOPCO CPF-II Facilities ProjectTTOPCO CPF-II Facilities Project was developed to establish crude oil production and processing capability in Koysinjaq, Iraq, delivering a facility capacity of 90,000 bopd.

Karya Engineering participated as the E&I subcontractor, performing Electrical and Instrumentation works and supporting the safe start-up and commissioning of the facilities.
Project Scope
15,000 m Cable Tray Installation
200,000+ m LV Electrical Cable Installation and Termination
MV & LV Substation Installation
1,455 Field Instrument Installation, Test and Calibration
Plant Fire & Gas Alarm System Installation
DCS & SIS System Installation
75,000+ m Instrumentation Cable Installation
Pre-commissioning Works
Services Provided
Construction
Pre-Commissioning
|Project Details
Koysinjaq, IraqInstallation and Commissioning of E&I WorksEstablishing 90,000 bopd crude oil production and processing capability.
CLIENT
Taq Taq Operating Co / Ventech
START DATE
February 1, 2015
END DATE
October 1, 2016
DURATION
21Months
COMPLETED MAN HOURS
130,000MH
STATUS
Completed